Definitive Delivery Agreement (Dec 2011)

In submitting the LDP before the end of 2011 Ceredigion County Council will have delivered the LDP in accordance with the indicative timetable (+3 months agreed slippage) set out in the Amended Delivery Agreement (DA) as agreed by WG at April 2010.

The table attached sets out the latest dates as moved on by the 3 months slippage allowed for in the 2010 amendment of the DA. The new definitive time table is still in line with the key dates in the original indicative version plus the agreed 3 months.

The Definitive delivery timescales is as follows as of December 2011:

Part 3: The Plan Managing Process

3.1       The timetable

Figure 3.1: Critical stages in the LDP preparation process (amended at December 2011)

Stage in Plan Preparation

Definitive Timetable

1

Submission and agreement of Delivery Agreement

June 2007

2

Pre Deposit preparation

June 2007 - January 2009

3

Pre-deposit public consultation

March – April 2009

Assessment of representations received & Preparation of Deposit documents

April 2009 - November 2010

4

Deposit of the LDP and related documents

December 2010

5

Publication of site allocation representations for inspection (2 part consultation)

May - September 2011

Assessment of representations received (Deposit LDP & Site Representations) & preparation of documents for submission

March 2011 – November 2011

6

Submission of LDP for Examination

Consultation regarding proposed focussed changes

December 2011

December 2011 – February 2012

Indicative Timetable

7

Independent Examination

December 2011 – December 2012

8

Receipt of the Inspector's Report

December 2012

9

Adoption

February 2013